Key Takeaways

  • Booking day gives you an Option to Purchase (OTP) for a booking fee, usually 5% of the price. The developer then sends the Sale and Purchase Agreement (S&P), and you have 3 weeks from receiving it to sign and exercise.
  • Buyer's Stamp Duty, plus any Additional Buyer's Stamp Duty, is due within 14 days of exercising. The rest of your 20% down payment is due within 8 weeks of the OTP date.
  • On a $2,000,000 unit with a 75% bank loan, you put in $500,000 of your own cash and CPF before the bank pays its first progress bill, plus $69,600 Buyer's Stamp Duty as a Singapore Citizen buying a first home.
  • After that, the developer bills by construction stage. Each bill is due within 14 days of the notice, and your loan instalment grows as the bank pays out.
  • At TOP you pay 25% and collect your keys. The 12-month defects liability period and your maintenance fees start soon after, so inspect early and report defects in writing.

Expert takeaway: Booking a new launch unit is the start of a 3 to 5 year process, not the end of the decision. The first 8 weeks carry the heaviest cash demands and the strictest deadlines, so line up your lawyer, your loan and your cash before booking day, not after.

In numbers: for a $2,000,000 new launch condo, a Singapore Citizen buying a first home with a 75% loan pays $100,000 on booking day, $69,600 Buyer's Stamp Duty within 14 days of exercising and $300,000 more within 8 weeks, before the bank disburses anything (IRAS Buyer's Stamp Duty rates; payment stages under the Housing Developers Rules, both as at October 2026).

Congratulations, you have booked a unit. Most buyers walk out of the sales gallery with a receipt, a stack of forms and one question: what happens now? This guide walks through every step from the Option to Purchase to the day the final payment is made, with the deadlines, the money due at each stage and the mistakes that cost buyers real money.

What happens on booking day?

On booking day you pay a booking fee, usually 5% of the purchase price, and the developer grants you an Option to Purchase (OTP). The Housing Developers Rules allow a booking fee of 5% to 10%, but 5% is the norm under the standard progressive payment scheme. The fee is paid to the developer's project account, not to the salesperson.

The developer must also complete customer due diligence checks under anti-money-laundering rules. If it cannot complete them, the option becomes void and the booking fee is refunded without interest, per the standard OTP wording updated by URA's Controller of Housing in August 2025. Bring your NRIC or passport and answer the source-of-funds questions fully to avoid delays.

Before you leave, check that the OTP shows the right unit number, price, names and the payment scheme you chose. Changing the names on a unit after the OTP is issued is not a simple admin step, so settle who is buying, and in what shares, before you book.

What happens in the first 3 to 5 weeks?

Within about 2 weeks of the OTP date, the developer sends the S&P and the title documents to you or your lawyer. You then have 3 weeks from receiving them to sign and return the S&P, which exercises the option. This is set out in the Controller of Housing's rules on the option period and in rule 11 of the Housing Developers Rules.

WhenWhat happensWho acts
Day 0 (booking day)Pay the booking fee (usually 5%); OTP issuedYou
Within about 2 weeksS&P and title documents sent to you or your lawyerDeveloper
Within 3 weeks of receiving the S&PSign and return the S&P to exercise the optionYou and your lawyer
Within 14 days of exercisingPay Buyer's Stamp Duty and any ABSD to IRASYou (your lawyer files it)
Within 8 weeks of the OTP datePay the rest of the 20% down payment (15% of the price)You (cash and/or CPF)

Appoint your conveyancing lawyer within the first few days. The lawyer reviews the S&P, files the stamp duty, handles your CPF withdrawal and works with your bank. Many buyers use the developer's panel firms, but you are free to choose your own. Our guide to conveyancing fees explains what the lawyer does and what it costs.

Accept your bank loan before you exercise. An In-Principle Approval is not a loan. Get the bank's Letter of Offer, read the lock-in period and the rate package, and accept it before you sign the S&P, so you are never committed to the purchase without confirmed financing. Compare packages on our latest mortgage rates page.

What if you change your mind before exercising?

If you do not exercise within the option period, the option lapses and, under the standard OTP form, the developer keeps 25% of the booking fee and refunds the rest. On a $2,000,000 unit with a 5% booking fee, that is $25,000 lost. Once you have signed the S&P, walking away is far more expensive: see our guide on the legal consequences of failing to complete a purchase.

When is stamp duty due after booking a new launch?

Buyer's Stamp Duty (BSD) and any Additional Buyer's Stamp Duty (ABSD) are due within 14 days of exercising the option, that is, the date of the S&P. BSD on residential property runs from 1% to 6% in tiers, set out on IRAS's Buyer's Stamp Duty page. On $2,000,000 it is $69,600. Run your own figure in our stamp duty calculator.

ABSD depends on who you are and what you already own, per IRAS's ABSD rates: 0% for a Singapore Citizen's first home, 20% for a second, 5% for a Singapore PR's first. Many buyers pay stamp duty in cash first and then ask their lawyer about a CPF reimbursement, if they qualify.

HDB upgraders who keep their flat for now: a married couple where at least one spouse is a Singapore Citizen pays ABSD upfront (20% on a second property, or $400,000 on a $2,000,000 unit) and can apply for a refund if they sell the flat within 6 months of the condo's TOP or Certificate of Statutory Completion (CSC), whichever comes first. There is no extension. That date is fixed by construction progress, not by you, so plan your flat sale around the expected TOP. Our HDB to condo upgrade guide covers the timing, and HDB extension of stay explains how sellers bridge the gap to key collection.

How much do you pay before the bank loan starts?

With a first housing loan at the maximum 75% loan-to-value, you fund 25% of the price yourself, and at least 5% of the price must be cash under the MAS housing loan rules. In practice, the 5% booking fee meets the cash minimum, and the remaining 20% can come from cash, CPF Ordinary Account savings or both, subject to CPF's housing withdrawal limits.

The bank starts paying only after your 25% is used up, which in the standard schedule falls partway through the foundation stage. If your loan-to-value is lower (a second housing loan, or a long tenure that pushes past age 65), your own share is larger and the bank comes in later.

What is the progressive payment schedule for a new launch condo?

Under the normal progressive payment scheme, the developer bills you as construction reaches each stage, backed by its architect's certificate. Each instalment is due within 14 days of receiving the developer's notice. Here is the full schedule on a $2,000,000 unit with a 75% loan.

Stage% of priceAmountTypically paid by
Booking fee (OTP)5%$100,000You, cash
S&P, within 8 weeks of the OTP date15%$300,000You, cash and/or CPF
Foundation completed10%$200,000You $100,000, bank $100,000
Reinforced concrete framework10%$200,000Bank
Partition walls5%$100,000Bank
Roofing or ceiling5%$100,000Bank
Doors, windows, wiring, plastering, plumbing5%$100,000Bank
Car park, roads and drains5%$100,000Bank
TOP25%$500,000Bank
CSC and legal completion15%$300,000Bank
Total100%$2,000,000You $500,000, bank $1,500,000

Stage percentages follow the standard S&P under the Housing Developers Rules. The split between you and the bank assumes a 75% loan. Plug in your own price and loan in our progressive payment calculator.

What happens during construction?

For the next 3 to 4 years, most of the action is paperwork. Each time a stage is certified, the developer sends a notice, your lawyer and bank arrange payment, and your monthly instalment rises because you pay interest only on what the bank has paid out so far. Early instalments are small; the jump comes after the TOP payment.

What happens at TOP and key collection?

When the project gets its Temporary Occupation Permit (TOP), the developer sends a notice for the 25% TOP instalment, due within 14 days. Once it is paid, you receive vacant possession and an appointment to collect your keys. This is also when your bank loan is mostly drawn down, so expect your full monthly instalment from here.

The defects liability period (DLP) is 12 months. Under the standard S&P it starts on the earlier of the day you take vacant possession or the 15th day after the developer's TOP payment notice, and your share of maintenance charges starts at the same point. In November 2025 the Government announced that this trigger would move to the 35th day after the TOP notice, to give buyers more time to collect keys and inspect, taking effect in early 2026 (Minister for National Development, 13 November 2025). Which version applies depends on your S&P, so ask your lawyer.

From TOP onwards you also budget for maintenance fees to the management, property tax once IRAS assesses the unit, utilities and home insurance. Owner-occupier property tax rates apply if you live in the unit.

How do you check and report defects after key collection?

Inspect the unit as soon as you collect the keys, ideally within the first week. Test every tap, switch, socket, door and window, look for hollow tiles, cracks, stains and uneven finishes, and photograph everything. Many owners hire a professional inspector for a unit this size.

What happens at CSC and legal completion?

The Certificate of Statutory Completion (CSC) is issued after TOP once the whole development meets all requirements, often months to a year or more later. The final 15% is paid around this stage and at legal completion, when the title passes to you. Part of it is held by the Singapore Academy of Law as stakeholder until the title is ready, which protects you if the developer has not finished its obligations. Your lawyer handles this end to end, and your bank pays from your loan.

What are the most common mistakes after booking?

Still choosing a unit? Read our step-by-step guide to buying a new launch condo and compare projects on the Insider Benchmark before your next booking day.

Selling your HDB to upgrade?

Know what your flat can fetch before TOP.

If you are keeping your flat until the condo is ready, your ABSD refund depends on selling within 6 months of TOP. Get a free, data-backed estimate of your flat's value and a sale timeline that lands inside that window.

WhatsApp: Free Flat ValuationCheck My Flat's Value

Frequently Asked Questions

Can I cancel after booking a new launch condo?

Yes, by not exercising the option within 3 weeks of receiving the S&P. Under the standard OTP form the developer keeps 25% of the booking fee, which is $25,000 on a $2,000,000 unit with a 5% fee, and refunds the rest. Cancelling after you sign the S&P is far more costly.

Can I use CPF for the booking fee?

Plan to pay the 5% booking fee in cash. With a bank loan at 75% loan-to-value, MAS requires at least 5% of the price in cash, and the booking fee usually covers that. CPF Ordinary Account savings can then go towards the next 15% and other stages, within CPF's limits.

When do I start paying the bank loan?

Only after your own 25% has been used, which in the standard schedule falls at the foundation stage. You then pay interest only on the amount the bank has disbursed, so your instalment grows with each stage and is largest after TOP.

When does the defects liability period start for a new condo?

It lasts 12 months and, under the standard S&P, starts on the earlier of vacant possession or the 15th day after the TOP payment notice. The Government announced in November 2025 that this would move to the 35th day from early 2026, so check which version your S&P uses.

Do I pay maintenance fees before I get my keys?

Your share of maintenance charges starts at the same point as the defects liability period, which can be before you collect your keys if you delay collection. Collect promptly once the TOP notice arrives.

This guide describes the standard terms for private homes sold by licensed developers under Singapore's Housing Developers Rules, as at October 2026. Your OTP and S&P, the developer's notices and your bank's Letter of Offer decide your actual dates and amounts. Figures are illustrations, not quotations. This is general information, not legal or financial advice; check with your lawyer and bank.